BLOCKS 4 and 5
The construction of blocks 4 and 5 are being finalised. Both are currently being prepared for final quality checks by architects.
BLOCK 4
BLOCK 1
We are planning to finish the construction of blocks 1 and 2 in approximately 3 weeks. Currently, we are putting wooden floors. Once finished, we will begin cleaning and polishing it so that there will be ready for final quality checks in 3 weeks.
BLOCK 2
BLOCK 6
We are placing the plaster ceilings and waterproofing the terraces. We will continue placing all the floors both inside the house and on the terraces.
BLOCKS 7 & 8
We are placing the plaster ceilings and waterproofing the terraces. We will continue placing all the floors both inside the house and on the terraces.
Block 7
Block 8
FOUNDATIONS OF BLOCK 9, 10, 11
The structures are being executed - bricks, concrete block, stone laid out.